Successful Undocking of FPSO Saquarema
FPSO Saquarema Successful Shifting at 2# Berth
On 2, June, 2014, FPSO Saquarema was successfully undocked from 1# drydock after all DD2 work finished as schedule.
This drydock work lasted 73 days, mainly including hull and double bottom tank coating, over 2700t steel work, and other relevant piping, mechanical, electrical, and underwater work.
During the docking period, the work morale of whole project team had come into a new climax. In order to catch the schedule, workshops had overcome the difficulties caused by cross work and bad weather, comprehensively arranged the work, and enhanced the cooperation between all trades, which had made tremendous contribution to the progress of project schedule.
After shifting at 2# berth, FPSO Saquarema will definitely receive a new round upsurge in construction. The project team will exert their utmost effort in the following days and b